Work on the Shrine of ‘Abdu’l-Bahá is advancing steadily across the site, with several of its most intricate stages now simultaneously under way. 🏦
The marble cladding of the trellis and columns of the central edifice is being undertaken, with five columns completed and three still to follow. The folding walls along the central plaza are being fitted with local stone, while the curved interior walls of the central edifice, framed from components precisely cut and prepared years in advance, are assembled like a mosaic. The glass panels, the tallest standing at more than eleven meters, have been fabricated and delivered, and await installation by a specialist team in the period ahead.